The general procedure for setting sidetracking cement plugs is to: 1. SET a 300 - 500 ft neat cement plug (Class G in the production hole section) at 17.0 ppg (batch mix the slurry if possible). 2. WAIT on cement for 12 hours minimum. 3. DRESS OFF 20 ft, and WEIGHT TEST the plug. 4.1If the plug is firm